My experiences of house construction


Building a house is a huge task which demands time, energy and strong nerves. This is what I feel after I started construction of my house at Media Town Rawalpindi on September 28, 2010. I am indebted to Mr Mujtaba Shahid who guided me from first steps and he continues to give advice and his time. I am really on a very tight budget as the investments which I had made in real estate have rally gone at the lowest ebb. A bad time to sell, but have to build now as later hike in construction material is imminent, especially in the wake of massive monsoon flooding in Pakistan which has affected 14 million people.


3D sketch


I got the possession of plot (2800 square feet) in April 2010 and contacted Jamshed and Associates for designing and layout. The process was finalized by July after several sessions and heated discussions with Mr Najib Kayani and within the family. Then I decided to have the soil of the plot tested and here the things really became challenging as the soil analysis revealed lose fill and recommended six-feet-deep excavation and then refilling it up to three feet with compaction. On the rear (western) side of the plot a two-feet wide retaining wall was encountered, which the developers claim that is eight feet wide at the base and rises up to 40 feet and the peak height was 45 feet from the ground level.


Map of A Block, Media Town, Rawalpindi


But stone wall is a negative and it should have been a concrete wall. The developers claim that it was absolutely safe and built according to standard practices and there was no chance of its settling down or cracking.


Meanwhile, I applied for water, electricity and gas connections. Water line is connected, though the supply is still erratic as water lines were damaged during underground power cable installation work by Islamabad Electricity Supply Company (IESCO), according to the developers. The repair work is going on and meanwhile water for construction purposes is being provided through tankers. Electricity connection normally takes three weeks, but the process was accelerated, courtesy by a friend. On October 1, I applied for natural gas connection, well in advance because the gas company normally takes at least six to 12 months to provide a gas connection.


Ground floor plan


I have to arrange enough water, through the tapped supply or tankers to flood the bed and after it is well drenched for couple of days, and then hire a road roller for compaction. Getting the road roller into the pool would also be a challenge.


First floor plan


Also have to go to 10 Corps Headquarters, Chaklala, where the power company office is located in very high security zone, to collect the demand note and then have to go to bank to deposit installation charges.


A temporary store has been built near the construction site with mud and bricks to store cement and provide accommodation to a full-time security guard. I hope that once this compaction thing is done, things would start moving at a pace.


October 5, 2010


Soil analyst on last visit on Monday recommended compaction by a 18 tons road roller which has vibrator after amply watering the bed. The search started right away. Today morning I started around nine and reached the site and checked possibility of running tap water supply, but the underground lines were still damaged at several points. Then along with my contractor we went to DHA phase one, picked up a guy who joined our search for a roller. In Rawat we found one, but it was 12 tons and no vibration. So left it as a last option and tried to search more, but so far in vain.


Went to Chaklala garrison IESCO office to collect demand, not. Had to queue up for about 20 minutes at garrison gate. Do not understand why do not they move IESCO office out in civilian area. The IESCO staffer asked me to get six copies of the demand note from Shaheen Market and come back. He then kept one copy in his file and told me to submit 25,500 rupees in Allied Bank, Old Chungi Branch, Chaklala Scheme III. Went to bank and thanks God there was no rush at all and it took just three minutes to submit the fees. IESCO guy said that in seven to eight days connection will be given.


Traveled back to Media Town and then had a meeting with the architect at PWD society. After several calls and running around, got the tap water running, but the supply was short lived only for 40 minutes. Then a laborer spotted seepage into the whole of underground tank from the water supply line. Called the lineman and he said he had called it a day and will check back tomorrow.


Tap water supply inauguration


I ate two bananas and glanced through some unread pile of magazines as I called and text-ed many people checking the availability of a road roller. Meanwhile a steel bar dealer and a salesman for termite treatment company visited me while I was camping in my car. Also visited the building material supplier and paid his bills. Also paid sanitary store bill. As of today 152,000 rupees have been spent on construction project and all I have is a dug up plot, a temporary site store room, water connection (so-called), electricity connection (in papers).


October 6, 2010


with the grace of Allah, many hurdles were crossed today. I thank Allah for a great day as all the things which were stuck and hit by snags, suddenly fell in line with so much ease and convenience. I also again... learned to be more patient and consistent and keep trying while continue to seek guidance and blessings of Allah.


Started the day around 8:30 at site. For next 90 minutes, had no clue about road roller and water and was thinking about to abandon the road roller project and go ahead with normal compaction. At around 10:00 am went with contractor in search of a road roller and after asking couple of excavator guys finally found one parked silently amid shopping plazas behind United Bakery in PWD housing scheme.


Called the cell number written on the roller and it was booked right away for an advance payment of (4,000 PKR + 20 liters diesel price) at a nearby real estate dealer office. The guy with whom I spoke on phone came to site to see if the roller could work there or not. The nearer the roller is to your site, the less expensive it will be and I was lucky to find it so near, while everyone was telling us that we should go to Rawat, Tarnol or Pirwadhai for it--a long travel for them to reach Media Town.


Then went to building material dealer in Police Foundation colony. Ordered 35 bags of cement, gravel and sand for starting the construction of underground water tank.


Water tankers were arranged from PWD, but later site supervisor came and promised to water the bed, so the order was canceled. I took a risk on supervisor's requests. On Thursday I have to go to Federal Government Employees Housing Foundation (FGEHF) in connection with the sale of a plot as funds are now badly needed, so it will be a lot of traveling between Islamabad and Media Town and after the roller has done its work I have to again go and bring soil analyst and then again drop him in Chaklala. I have realized that 100 kilometers drive in city is much much more tiring than six hours drive on highways.


October 7, 2010


Another jinxed day. The roller came to the site and refused to go inside the plot saying it was too much over watered. Damn! The water guy had promised yesterday that he will drench the site by 7 am, but when I reached around 9 am, he had just finished watering it. I fail to understand that why people commit things which they cannot do or deliver.


For example here you tell a guy 20 times that will he show up at 8 am sharp next morning and he will swear upon anything saying that even if Heavens fall he would show up definitely. The next morning you go at 8 am and there is no trace of the guy. So far I have only found the building material dealer so quick that orders have been delivered super fast according to the time. Rest of the departments are really never wrecking.


The roller operator said that his machine will be stuck, while site supervisor was saying that it would not as the soil was sandy and there were too many stones and water will be absorbed in an hour or so. The operator waited till lunch time and then again refused to do the job saying there was water. I am getting sick of muppet after muppet appearing clueless about how to proceed further on compaction job.


The biggest shock came from my contractor when he asked me that how much we are going to fill and if we fill up to road level and compact it we will need 20 dumpers of gravel, something like 200,000 rupees just for gravel for filling? The way he is doing the work without any brain, it seems that he will spend my one million rupees just on foundations. I have arranged two meetings between the contractor and the architect and my soil analyst has talked to him several times and still he does not know what to do.


One of the most important lesson from this story is that never follow a proper path or never adopt proper procedures in doing anything in Pakistan, because you will be stuck big time due to empty brains all around you. They are just good at what they have been doing since childhood and soil testing, compaction, raft foundations is too much for most of them. Almost every tom, dick and harry who visit the excavated site come and say oh that was not needed, you have made a huge unneeded expense on digging up the site, now how will you refill it?


I had been hearing from many people that house building can make you a crazy psychos. Now I understand how it grinds. But then I see all around, the endurance of fellow humans who have undergone such a treacherous task and still surviving.


I think every journey you take from your home for some work is so eventful that you can write a blog post daily. Now tell you another ordeal which I faced today.


I sold my tiny plot in G-14/1 to start construction. The stupid purchaser gave time of 11:30 am for plot transfer. I left my construction site unattended and the muppet turned up at 3:40 pm from Peshawar and that too with a DD in the name of Mohsin Hassan Gilani.

I had specially asked the agent and written in ...bold caps my full name for the DD (Bank Demand Draft), but the idiot gave totally wrong name to the purchaser. I wonder why my parents gave me such a difficult name which everyone misspells and I have suffered a lot several times because of the poor clerks who cannot write it correctly both in Urdu and English. All these estate agents are really big frauds and totally cheats and incompetent lot. They purchased from me and sold to another guy and made 110,000 bucks extra. They always take the seller taken for granted knowing he needs money big time and would do what they like.  The purchaser gave a cheque of Allied Bank, which G-10 Markaz branch refused to cash because it was way beyond the allowed online transfer limit, though the account had the balance (stupid limit). Have to take risk and accepted a crossed cheque. After all a bounced cheque can get the issuer behind bars, so I hope that my ordeals just ends here and cash comes through by next Tuesday. I would have straight away refused the deal, but purchaser's uncle came out to be an acquaintance.


October 8, 2010


Roller in action


When I was thinking of getting out of bed early Friday, wife told me it's raining outside and I said to myself what else could go wrong. Last week I had been praying for rain as wanted to drench the plot but it remained very warm and sunny. A full day had already been wasted because of the stupid water supply staff, the road roller operator refused to press the bed being two muddy.


But as soon as I left I-8 and moved on Islamabad Highway in the direction of Rawat, there were hardly any signs of rain. So the rain was only in Islamabad. I was so happy and thanked Allah for not sending rain to Media Town. But was disappointed to see roller operator sitting on the roadside. He told me that the bed was still too muddy, but the real thing was that his machine was not starting due to bad battery. We tried a jump start with my car, but it did not help.


Made calls to site supervisor as he has a diesel powered Suzuki jeep, but he was absent today. The owner of road roller was also not present in the area and he said that would be reaching in two hours. Went to PWD market and brought an electrician with a very heavy battery, but his battery had very little charge. Went back to drop him and on way back to the site stopped over at architect office. As usual he was not present. His assistant had no idea about the design of raft foundation initially as he is a new person. After sometime he said that he had understood my case and promised (in Urdu it is called giving a goli) to give me the drawings in two days.


Then stopped over at building material supplier's office to pay bill. The man talks too much, but his material is ok and supply prompt and no headaches so far.


Contractor started work on underground tank. Tomorrow I will buy steel bars.


October 9, 2010

Morning after road roller press


Woke up early around 6:15 am went to Askari 10, picked up soil analyst and his team and took them to the site. They inspected and declared it fit for further compaction up to four inches layer of the excavated material. Sides and corners would require manual pressing. He further advised that if the DPC level was five-feet then more filling had to be done.


The material taken out would be used in filling foundations once they are raised on a raft which is being designed and expected to be ready on Monday. Architect said that it would be minimum 8 inches thick, while soil analyst says the minimum requirement is 9 inches.


Work on underground water tank started, which also a major expense in any construction. We need this tank first thing as water supply is still not repaired and we have only four drums of storage. Will try to get more drums from company office.


Soil analyst visit also saved me from making a big expenditure on buying filling material (cut stone). The contractor had said that about 20 truckloads of this material would be required and he was wondering why we would use the same material which we had taken out. I think it is the first project of his life of this nature where things are going systematically and in the light of advice from technical experts. Now the contractor says that he would follow what engineer and architect will tell him.


October 10, 2010


Construction of underground water tank begins


Purchased steel bars worth 23,700 PKR for underground water tank. Also purchased steel binding wire for 775 PKR. Got four more drums from construction company store for additional water storage as the construction of UG tank begins Monday morning. The contractor insisted that I should buy steel bar from steel mills in Islamabad, because all the steel dealers in area were providing low quality steel and their weighing scales were tampered. Mr Shahid contended that the vendor was ok.


October 11, 2010


Construction of underground water tank


There was heavy rain early Monday after a frightening 5.3 magnitude earthquake, but the weather cleared by the time I reached the site around 9.00am. All day laborers kept pouring concrete in the shuttering. Thankfully the material and water were sufficient for the day. Bought some diesel from PSO Bahria and gave it to tanker driver so that he keeps filling the drums till the UG tank is ready for water storage. I was really exhausted by the end of the day.


October 12, 2010


Took a day off from everything to give myself some badly needed rest. Contractor called in the evening to tell that tank was plastered further work on inner walls would be done in couple of days after which compaction work will start. A big relief came in the evening when funds were transferred into my account.


October 13, 2010


Underground water tankUnderground water tank


Visited the architect and asked him to complete the work on raft drawing as soon as possible. He cited computer crash as a reason for delay and again promised that it will be delivered by the end of day. I keep my fingers crossed. Called electricity office and they were saying that since meter and other stuff was not issued yet, I should wait till next week. On my asking he agreed that it would be next week. Heard from other people building their houses that IESCO officials came and installed connections even they have not yet deposited their demand notes!!!


October 14, 2010


Architect is taking too long to complete and hand over raft drawing. Mehboob Hussain promised that he will call me when it is ready latest by the evening. It did not happen. Such things are too frustrating and delay things unnecessarily by days. Now I am sure that Pakistan will never become a developed country, at least for the next seven generations.


Despite contacts in electricity department, no signs of electricity. The losers do not have to do anything but a put a meter there as all the underground wiring, transformers and cabinets are already installed. One of former colleagues who is building a house nearby said that the IESCO people installed electricity even they had not got any demand note and just on a simple application, next day power connection was given!!!


After estimating the cost of construction on underground water tank which is some 50K, I was wondering why I did not go for my own well. A 200-meter bore would have cost around 100K.


There is only one tractor-pulled water tanker without a pump which supplies water to over a dozen construction sites in Media Town and for each visit they require at least 1.5 liter diesel. They are not still able to repair the water pipeline yet and during these three weeks I have been going there, not much work they have carried out yet.


I hope that issues like lose filled plot, excavation, compaction, raft drawing, delays by the architect, electricity and water department do not drain your energies and you run out of patience and time.


October 15, 2010


Revised structural drawings


After Friday prayers I got the revised structural drawings in the light of soil analysis report. Met contractor and had a discussion about it. He said that tomorrow chips work will be done inside walls of underground water tank. Ordered material so that the work could get start on time tomorrow. Asked the contractor to now expedite work on compaction and raft-type foundation.


Good to see Bahria Town road department repairing the PWD-Police Foundation-Media Town road which was a pain to drive due to pot holes. I think all residential societies should follow the service provision model of Bahria Town.


October 16, 2010


Underground water tank


Underground tanks in-lining work was done today. This tank thingy is too expensive and time-consuming. Came to know that IESCO has run out of electricity meters, so further delay in power connection.


Thinking about going for building the two floor structure and then go step by step from ground floor. People say that if I make a single story now, first it would be too hot in summers and secondly would be more expensive and difficult and messy to build first floor later.


I may go for a brick structure after consulting the architect as steel column beam structure would be more expensive. Have to ensure safety and during a meeting with architect two weeks ago it was discussed and he said brick structure was more flexible to absorb earthquake shocks, while in column structures brick give in to shocks and then the entire weight is thrown on columns which get twisted.


October 18, 2010


compacton work starts


Left the home around 8.30 am, reached the site just before 9.00 am. Went to society office for requesting water tanker. Then went to plot and laborers had started laying the four inch layer as directed by soil analyst.


October 19, 2010


First water filling in undergraound water tank


Went to site after finishing office. Contractor is facing some family issues. So his second wife's relatives who were working as masons have left him. Now he has asked me to arrange a guard for the site. Earlier those masons were staying at the site during the night. Second worry is power connection which is badly needed as on Sunday the contractor plans to lay the concrete. If no electricity, no work as water pump would be needed for the entire day for concrete mix.


I have ordered 65 bags of cement, gravel and sand. Steel will be purchased in next couple of days which is a major expense. I am thinking about getting a temporary connection, but do not know if it is possible. Another demand by the contractor is that I will have to provide lunch to all laborers (a deg) on the day, as if I am a free person and do not have to do anything else. While work related issues remain unresolved, he is more concerned about free lunch.


It was really a tiring and stressful day. Trying to not think about the project issues anymore as have to deal with unruly kids at home :-)


October 20, 2010


Electricity meter is being installed


Sent text messages to several people seeking help for electricity connection. An old colleague in water and power ministry finally responded by replying to sms saying it will be done today. He had not been taken my calls, may be he had lost my number.


I also sent SMS to Afzal Butt, our journalist union leader, but someone told me he was visiting US. My PakWheels.com friend who had a very senior contact in power company had been constantly following up the effort. He said he was on it on daily basis. I also sent an sms to IESCO director public relations, but no response.


Today was my off day. After breakfast headed to media town. Visited the architect to check that if we could go for a brick structure instead of very expensive steel columns structure. He replied though there was nothing wrong with brick structure, but I should go with the suggested steel column structure because it was according to latest NESPAK standards. Also checked with him if the amount of steel bars suggested by the contractor for raft foundation and couple of columns in porch was appropriate. He said it was ok. Now have to buy more steel.


Contractor still insist that brick structure will be as good because there is no guarantee that a steel-column structure will withstand a massive earthquake better than a brick structure. Despite high cost have to follow architect. After estimating the price and amount of steel required, I think that my funds are going to be depleted very fast which is a worrying factor. Let's see if something extra-ordinary happens before I run out of steam.


Later, called the IESCO official and he said today connection will be done. He asked me to contact another guy, but that chap said that I should call him after 4.00pm. I waited and waited and when called him, he said it was not possible today, he was bringing stuff from store and it will take a very long time unloading. I headed back home and when I was near Faizabad, the guy called and said that I could come now and he will send personnel for installing the meter at the site. Surprisingly he was just adjacent to Media Town, behind the grid station. I never knew they were so close, otherwise had been pestering them myself daily.


I also bought a switch board and thanks God the main line was working when he connected wires with it. So a major worry is over today, thanks to my friends.


October 21, 2010


One hp motor


Bought electric water pump. It is a vital equipment during construction. The shopkeeper asked whether I wanted one horse power or half horse power one motor. I had no idea. After consultation I went for one horse power, which means more power consumption, but quick turn around. The motor itself was for 5,ooo PKR and another 1,220 PKR for pipes, hose, filter, power cable and switch.


Requested a water tanker for Saturday. Will need another on Sunday. Line repair is still going on. Water supply is a big problem at them moment in the area, but free tanker service is available.


Oct 24, 2010



Concrete mix laying


If a vendor tells you that the equipment you have just bought is test and working and he will immediately return if it did not work never believe him and insist for a test run. On a sunny Sunday morning concrete mix spread (1:4:8 or 4:1:8 or whatever) work was to start. Had bought the water pump motor on Thursday because markets in Rawalpindi are close on Friday and on Saturday I had a full day at office.


On Sunday morning I reached the site at 7:40 am. Unloaded the motor and placed in on the head of underground trunk and when hooked to power it did not start and caused a burnt fuse. The fuse was redone and this time there was a whining noise but no movement. Called the shop from where it was bought and he said electrician would come late and if I could bring the motor to shop, it can be checked and if necessary replaced right on the spot.


I took the motor and after waiting for about 10 minutes an attendant checked it and found that the fan fins were lose and were causing the jamming. Once screws were tightened and spindle was moved by hand, it came to life. I took back the motor and when it started pumping water another problem was encountered. The hose pipe was shrunk on suction, but since it was one horse power motor it did the job well noiselessly. At the end of the day got this hose replaced with a hard black one.


Seven laborers who came with the mixer machine and our regular three (one of them an aged man) did a fine job with untiring fast pace. I paid for their tea and lunch and they were happy to mix and pour a thick layer of concrete on 2800 sq feet area. The sand, gravel and 70 bags of cement cost me more than 60,000 PKR. Tomorrow will go to I-9 sector to purchase steel bars. One steel factory is offering special discount to Media Town, so will try that.


Overall the day was not as touch as I was fearing. Contractor also returned from Bahawalpur after resolving his family issues.


My dear car is getting dirtier as there is lot of dust it has to drive through and I have been left with no energy to keep it clean :-( Have traveled 1,500 kilometers since the project started.


October 25, 2010


Concrete mix laying


This online banking is a farce, never works when you need it most. Nothing in Pakistan is without any snag, hitch or glitch. Had to travel to my branch in Aabpara Market for cash, as the one near my home could not fetch my signature on their "system."


Today's mission was to purchase some 4,150 kilogram re-bars or sariya from Ittehad Steel in I-9 sector. They are offering special discount to Media Town. Paid some 253,000 rupees in the morning and the stuff was delivered by them on site in the afternoon. It was a hassle-free. Contractor and sariya work supervisor recommended to buy from factor instead of local vendors as they think that all of them are big cheats as they measure less amount of steel and their quality is not that good.


I was told at the factory that I could book the steel bars now and protect myself from impending rise in steel prices because the government is going to stop natural gas supply to industry and in that case they will have to switch to furnace oil which will in turn cause price hike. If I book in next couple of days, means pay full amount in advance, I will get the same price on booking day and in case the prices dropped, I will get lower price. Seems good option and they accept cross cheques as well, which means some withholding tax saving.


The freighter was lost in the way a bit, but I guided him through cell phone and the truck reached the site.


Also got a frantic call by contractor to come to the site immediately as he was marking the bed for laying raft foundation. He had some problem with the measurement and I asked him to follow what was on the paper and then he understood and did not bother again.


October 26, 2010


Steel arrivesMarkings for raft foundation


Checked the site before office and met contractor. He was happy with the quantity and quality of steel re-bars. He had marked the bed with red lines on which raft is to built with concrete and steel.


October 27, 2010


Steel work for raft foundation begun. Went to site around 3.00pm after finishing office. Ordered 100 bags of cement, a truck load each of sand and gravel. Got an estimate for steel requirement for the roof so that I can book early as prices are going to be increased in the wake of gas loadshedding.


October 28, 2010


Steel binding


Asked for leave from office today as wanted to go to Ittehad Steel to book steel. Shocked that there was 1000 rupees per ton price increase and in coming days it is expected that steel prices may rise by another 3-4 PKR per ton. Then went to site as the contractor had asked me that we had to buy marble waste for the foundation work.


When we reached crossing broken muddy roads in an area, he said it was his house and he wanted his family to come along to show them a plot in Phase 8 of Bahria Town.


First I was annoyed, but then thought that I had come so far and in the interest of good working relationship for the project I did not disgrace him in front of his family. I would have refused if I knew how far the Phase 8 was, I though it would be nearby chalo janay do. But it was far far away.


But on the way I told him that he had made me extremely tired and my car had become too dirty and squeaky after going on such bad roads and would require alignment and balancing and suspension work. I told him that I never take my car to such places where today he has taken me. I think the message will reach him. But anyways next time I am going to say I am busy, or I too have to go somewhere.


Another shock came when checked prices of bricks Peshawari bricks are selling for 5,500 rupees (per 1000) while ordinary ones were for 4,300 and 4,100. I require 25,000 just for foundation. Damn. I am going to finish my money on foundation and when I express my apprehension, everyone says continue the work, money will come from somewhere and I do not where is that somewhere.


October 29, 2010


After a long time took a break and did not go to plot. Slept couple of hours more and then did some shopping for kitchen and went to Metro as well.


October 30, 2010



The contractor asked me on phone yesterday to come early in the morning for concrete pouring work on the raft foundation. As I reached there, the mixer had not arrived and laborers were just busy in fixing wood planks to make ducts and put marble pieces under the steel net to raise it for the concrete pouring.


When I reached there 105 bags of cement, sand and gravel had already been delivered as promised by the material supplier. Water pump was fixed on the head of the underground tank. Thanks God there was no load-shedding and the motor worked very well. The concrete work was over in about three hours.


Bricks have suddenly disappeared from market and their prices hiked insanely by 400 to 600 plus. Tomorrow will check with supplier.


Today I got tougher with concrete mixer laborers. Even after three-hours of total work today they were demanding money for lunch and and tea and I said sorry, I can't pay every time and that too for a half-day job. Had they started the work on time at 8.00am they must have been free by 11.00am. Told them to get the contractor for this. The last time they worked full day for concrete pouring on the entire plot and I paid them for tea which was not binding on me but as a courtesy I paid for tea and also paid for their lunch, even it was not for the roof (lenter) work, which is a tradition. There is a "deg" large pot of rice or meat or both mixed is cooked and distributed among laborers as a charity when concrete mix is poured into roof. But my contractor was making me pay for every visit by mixer labor and this time I had to be stern and refuse. Charity is good thing, but being fleeced is another thing.


Told my contractor that he made me bring a drum for water for mixer machine which I later came to know was not my responsibility or my expense and I am going to fix him.  Actually I do not know at all how to deal with the labor and contractor. An acquaintance who introduced to me to contractor had asked me to be tough on him, but did not tell me small things for which the contractor had been making me run from pillar to post and I spent too much time, energy, money which was his job for which I am paying him too.


So beware and shun any attempt by laborers to ask for free food and tea. When the water tank is ready it is not your responsibility to arrange for drums for mixer. Tell your contractor to arrange it at his own expense.


Just got the news that security guard or chowkidar has arrived finally and now I have to buy him bedding and a cot. Will have to go after 6.00pm after finishing office on Sunday.


October 31, 2010


raft foundation almost done


Bad news which I got today was that bricks would not be available before Tuesday :-(. Means loss of half of week in starting the foundation. Plus the bricks would be more expensive than they were last week. Prices of steel and cement are also rising after every other day. The estimates are in a shambles as the unforeseen factors are exerting dominance.


Chowkidar or guard finally arrived at the site. He will take care of construction material dumped in the open. Only cement bags can be stored in the store room. People say that someone has to remain present on site round the clock, otherwise pilferage of different material starts.


Went to meet him in the evening and to hand over to him bedding and torch. He is a young guy from Buner and came through a reliable contact. Could not find a steel pipe cot for him in Pakistan Town and PWD markets. It is available in Car Chowk area, but the problem is that we have to pass through Bahria Town where you can transport thing out easily, but cannot exit with anything :-(. It is also expensive to source such a material from Islamabad or Murree Road, Rawalpindi. A friend in Pakistan offered a wooden cot frame which seems the easiest option so far, but it likely to be broken and damaged if many men sat on it. Tomorrow will go on hunt for it, till then the poor chap has to sleep on the floor, which I do not like. Small things like these are big problem in the area.


November 1, 2010


Waiting for bricks


Bought a cot for the security guard from Khanna Pul. I do not know the area and was lucky that two former colleagues from APP were accompanying me and one of them was familiar with the area. Put the cot on a cab and transported it safely to site.


Supplier told me that bricks availability was not possible before Thursday. Bad news.


November 2, 2010


Got a call from supplier that one truckload of bricks @4500 PKR was available and I told him to deliver it. Called the contractor, who said that he would do the markings by the afternoon and start brick laying work from Wednesday morning. Supplier said that he will try to deliver another truckload tomorrow. Let's see when this bricks shortage ends.


November 4, 2010


Brick work starts


Finally bricks were arranged and chunnai or foundation walls construction was started. I visited the site in the afternoon. It was a very pleasant evening with a few clouds and light soothing breeze. It was a wonderful feeling seeing the foundations rise.


Prices of bricks have gone up. Paid 77,400 PKR for only 18,000 medium quality bricks. Now need about 7,000 more bricks for foundation.


I had to go back to site after two hours because police arrested two of the labourers who work on my plot and also live there in store shed. They were arrested alongwith all those others who were taking dinner at a food stall, just because they did not have CNICs.


What a miserable life for poor in Pakistan. Most of the chaps in lock ups had no acquaintances and they will be dragged in courts and then sent to jail before the relatives from remote villages reach and spend a lot money in courts and jails to get them released and this will burden them with more debt and loss of income due to confinement.


I made countless calls to various police officials, finally an old uni friend came to rescue, though he is no more posted in Islamabad.


When I stopped over at market on my return home the SHO who had disappeared when I reached the Karal Police Station, called me and asked me why I was calling him as he saw a lot of missed calls and I said you called me and then went on meeting (hiding) and he asked me if my labourers were released and I said yes and then he asked did his staff bargained for their release and when I told the name of the senior police official who ordered the Muharrar (policeman) to release the men, he suddenly said OK OK thank you sir and hung up.


In Pakistan if you do not know someone up at high places you are in serious trouble. Ghunda Raaj, police gardi. Thieves, robber everywhere, at shops, businesses offices, everyone is looting everyone he can and is looted by the big fish on his turn. $uking crabs in a basket.


November 6, 2010


Foundation brick work


Brick work of foundation continues. Nice to see walls rising. One more leak detected in the main water pipeline. Got a tanker of water and later tap supply was good enough even after watering bricks and walls.


November 7, 2010


Foundation brick work. More bricks arrive.


More bricks arrived today. Foundation walls seem to be finishing tomorrow and then filling will start. This stage has consumed nearly 800,000 PKR which shows how crippling is the recent price hike.


November 8, 2010


Shuttering for plinth beam fixed


This foundation seems a never ending project. Today shuttering was affixed and concrete beams (plinth beam) now would be built on these walls. Project costs are escalating beyond imagination as the recent steep price hike has shattered all estimates. After the plinth beam all these wells would be filled up which means another huge expense. Nealy a million rupees spent up to this stage. -:( Steel workers arrived around sunset.


Ordered 45 more bags of cement and asked the suppliers to stop delivery of bricks for the time being. I will need them mow after Eid holidays which start from 16 Nov and the labourers take at least 10 holidays.


November 10, 2010


This is taking tooooooooo long


Could not go on site round yesterday due to some pressing issues at home. Today when I visited the site, contractor was there. He showed me the leak from the water supply pipeline, the worst leak I saw since I began construction. The developer has done really a poor job with infrastructure. For the last three months I am seeing them repairing the leaking pipeline. Today I had to shout at them on phone to come and replace the broken pipe immediately as the water was seeping into foundations from under the boundary wall. Also asked my chowkidar (security guard) to inform me immediately if something like this happens. He does not seem to understand Urdu. The contractor is doing the plinth beam concrete filling on Thursday, but I have to go to Lahore to condole the death of a cousin.


November 12, 2010


Plinth beam


Plinth beam was done yesterday. Next stage is filling up to DPC level and that is now possible only after two weeks, because labourers go home for Eid and do not return easily. Paid 80,000 PKR to contractor according to agreed schedule. Finally I have decided to build only brick walls and not steel column structure after cost-benefit analysis and consultations. Contractor also suggested that we could have steel columns in the four corners.


The chowkidar or security guard who joined on 31st October today told me that he was leaving the job from 15th Nov because he was not happy. His presence was required during Eid holidays when thefts are more than usual and he wants to go on Eid holidays? I usually work on Eid, so why can't he? For what the security guards are paid after all? I told him that he could avail Eid holidays after Eid when other labourers who live with him in the store room return, but he is too adamant to go for no reason. People want easy money here. Search for next muppet is on.


November 13, 2010


Plinth beam


Went to vendor and paid him for the cement. Then went to site and asked the security guard what was his problem. He said that he had some enmity in the village and some resolution was in sight during Eid holidays. He said he was happy to work here, but leaving in extreme compulsions. He also said that he was safe here than in village and he had good income prospects as well but he had to go. I told him that he was leaving me in the lurch as finding a replacement just before Eid was almost impossible and costly material like steel, bricks and other stuff would remain unguarded. I have asked a cousin to find someone and he had told me that before 15th he could get someone. Let's see.


November 15, 2010


Sprinkling waterNew chowkidar Ijaz


Today went early for the change of guards at the site. The new guy came through a cousin who knows his brother working in his street . He does not have a CNIC and carried the photocopy of his brother's CNIC. Since his brother and the contractor are known to my cousin, so it will be fine. I would not have preferred him, but he was the only option left available during the Eid holidays. Have taken his photo, in case. The old one was younger and tougher Pashtun, this guy looks weaker than him. Let see how he performs.


Today taught the new guy, Ijaz, how to operate the water pump and sprinkle water over the beam and walls. House building is indeed a tense job. Due to security guard issue had to travel last night for the interview of the new one.


November 18, 2010


Rayan spraying pain on iron rodsA cloudy evening visit


A friend suggested that I should mark with paint the iron bars lying on the site so that if someone steals some, I could know and ask the security guard. So on second day of Eid, I decided to go to construction site. My son is very fond of going there too and he was annoyed on Eid day because I did not go there. Plus the visit had become essential to see what the new guard was doing. So when we went there, we found him busy showering water on the beam and walls. Gave him some more money as advance of his salary so that he could buy food. So far he seems to be ok on the job.


November 28, 2010


Filling of foundation


Today filling work was done. Reached the site at 7:30am. After half an hour excavator came. It is typical with filling workers that they demand extra after starting the work. The guy demanded 15,000 PKR for the work, but agreed on 13,000 to do the complete work and bring extra earth if needed. When half of the job was done and existing earth was almost consumed, he demanded extra 2,000 rupees which I refused firmly. He said that the tractor-trolley had to come from far away so the cost will increase. The vital thing is that make a firm deal that in this much money, such and such things would be done.


Above all my contractor said that at least 25 trolleys would be required. But only six did the job, rest of the material we got from the back side of the plot. Now I am really up set about the metal condition of my contractor and never going to rely on his estimates. He had estimated the cost to be around 25,000 PKR. I ended up only in 13,500. Paid the filling man only extra 500.


Also have plenty of steel left, which would be enough for roof. And the 4,200 kgs which I have booked would now go to a friend. These guy are very bad at estimates.


November 30, 2010


After filling


Today extra fill was being removed and beams were being cleared for DPC work. Bought DPC plastic sheet, Betaflex and brush from PWD market. Visited the architect and got details of doors and windows measurements which were missing.


The steel columns which we are not going to build were cut from the base. I have decided to construct steel columns only on the four corners and two on the corner which comes on the retaining wall. It is a cost saving measure basically as enough fortification has been done at the foundation. A truckload of sand and 35 bags of cement were ordered in the morning were being delivered when I reached the site.


I have started thinking about changing the contractor as he is do dumb and bad at anticipating things and suggest any solutions of even minor problems. I do not know how he is building or have built so many houses. Have paid him up to door level and when he reaches there, may say him good bye.


December 4, 2011


Wall construction begins


Today walls construction or chunaiyan began in the afternoon. DPC was completed a day ago with plastic and bitumen over another layer of cement on the plinth beam. Demand for sweet from labourers was firmly rejected.


Water supply is becoming a pain again and I am mulling digging a well or bore in local language. A costly affair, but if done correctly can free me from worries of water hunting. Will see a couple of guys tomorrow. Bought diesel in pet bottles to give it to tractor-tanker for supplying water as the piped supply has again failed. For the last three months I am seeing the never ending pipeline repair work. The contractor has put a very low quality pvc pipeline in Media Town. Whenever they run water from the well head, leaks appear like Wikileaks everywhere. Have very limited funds available, but I think that having own water supply is worth it.


December 5, 2010


progress on dec 5


My greatest worry is now water. Today checked with water boring guys adjacent to Minhas Corportation in PWD marekt, they said that the cost could be around 100,000 PKR, with ifs and buts that if stones were encountered it might shoot up. He was quoting labour like 140, 170 per with metal casing. People are advising plastic casing. I am double minded at the moment. Everything you do here has many pitfalls and a larger dark side. First boring is too expensive and secondly there are so many chances of its failure.


I doubt the capacity of the society to manage a proper, regular and predictable water supply system. So far nominal tap water supply has come twice or thrice in the past three months since I started construction.


When WASA tanker was here before Eid, there was no problem and was available on just a phone call free of charge. Now water supply is again into the hands of "company" and you have to make lot of calls to get water from their tractor-tanker and also provide them a 1.5 liter diesel bottle for each visit. The problem is that when you need the water most, they are not helpful then and this sometimes causes stoppage of construction work.


December 8, 2010


Wall construction progress on dec 8


Today was wasted due to lack of water. Media Town people also excused themselves because of electricity fault in tubewell's energy meter. I asked the contractor at 8.00am to finish his breakfast and arrange a private water tanker and start the work, but the goof reached there well beyond 10.00am and the sent the labourers on leave and ordered two water tankers. So basically he wasted the money on water and then the time. I also noticed that he has not left the door's space on a wall and has totally forgotten to make place for the powder room under the stairs. Will take him to task tomorrow morning as I will be on leave for next few days to spend more time to check his blunders. Ordered 6000 more bricks today as on Friday everyone goes on leave in the local market, at kilns and the truck drivers.


December 9, 2010


Walls construction progress on dec 9


Today gave a hard talk to contractor for forgetting the door of powder room. Mrs and Mr Mujtaba visited the site and based on their experience of building several houses, suggested some modifications which were done immediately as the walls had just reached chest level. They suggested a L shaped wardrobe in the dressing room and widening of windows of second bed and kitchen. Kitchen outer door was reduced from 3.5 feet to 2.5 feet to make room for a wider window and sink counter. Also decided to take the porch roof on the roof level instead of building the lower terrace which is just a waste and pain to keep clean. A tip to share that as soon as the walls (chunaia) start decide where you want to make shelves in the walls to keep decoration pieces.


December 11, 2010


Reached door level


Today wall reached 7 feet level or the door level. Steel workers arrived and started fabricating doors and windows beams. Once beams are done, probably within next week, brick work will resume till 10 feet. So far have spent about one million rupees.


December 12, 2010


Doors and windows beams shuttering in progress


Bought a 3 inch dia pvc piep and elbow for grouting inside the beam to serve as a concealed drain pipe. Windows and doors beam shuttering was in progress.


December 14, 2010


Columns being filled with concreteMy contractor Ghafoor and his daughter Ayeshabeam filling day


Today beams were filled with concrete. Thanks God water tanker arrived in the morning. I had to wake up early to pester the tractor driver to deliver water. He told me that tractor's oil filter was leaking. There is always some problem when I need the water for construction, despite I am giving a 1.5 lit bottle of diesel on every fill.


December 15, 2010


Columns unfolded


Today the beams and columns which were filled yesterday were unfolded (their wooden shuttering were removed) and the last column in the porch was filled. It was good to see tank full of water. Today another virtual friend Mr Atif visited the site. Thanks Atif for taking out time from your busy schedule and paying me a visit.


December 18, 2010


Wall construction progress on dec 18Water supply comes alive after months of outage


Today the work resumed after two-day Ashura break. Walls will go up from seven feet (door level) to 10 feet height till Monday. Ordered another truck of bricks. The most lively moment today was the restoration of piped water supply which came to life after about two months. Pressure was good and the company guys said that from now onwards there will be daily water supply.


I am now again thinking about building the upper story structure and then start finishing the ground floor because later it would be very difficult to do it and the cost will also rise. The thought is that once structure is done on the first floor, it can be completed later in phases depending on savings and availability of funds.


At night there was some debate about the high cost of labour. People are suggesting me that having gained the experience I should build the first floor myself and save on labour costs charged by the contractor. Seems good proposition, but it requires a lot of time and searching the right labour and it is not possible when one has a full time job with erratic schedules.


I am posting some details about my contract.


I have hired a contractor (for labour) @ 175 rs per sq feet (covered area 3820.49 sq feet) and the following schedule for a 10 marla (2800 sq feet) house.


Advance : 85,000 rs
DPC level: 80,000 rs
First door level: 45,000 rs
Roof level: 20,000 rs
Roof or lanter: 90,000 rs
First floor door level: 45,000 rs
First floor roof level: 20,000 rs
First floor roof or lanter: 90,000 rs
Tank, boundary wall: 40,000 rs
Ground plaster: 45,000 rs
First floor plaster: 45,000 rs
1:4:8: 20,00 rs
Ground flooring: 40,000 rs
First floor flooring: 40,000 rs
Bathroom: 20,000 rs
Kitchen: 20,000 rs
Roof concrete: 40,000 rs
Final 66: 42,889 rs


 









































































 

Area



Rate (PKR)



Total (PKR)



Covered ff/gf



3820.49



175



668586



Shades/pardi



114.25



87.5



9996.87



Chunai



2311



19



43909



PC



310



15



4650



DPC



155



20



3100



Top roof concrete



1752.31



30



52569



Terrace floor 1.4.8



376.62



30



11298



Gali floor 1:4:8



1047



30



31410



Plaster P&b/walls



3072



10



30720



Plinth



33



50



1650



 


Water tank ground                                                         50000.00   rs
Water tank up                                                                 50000.00   rs


Total: 957,889 rs (about 10 lakh or one million rupees labour total). Measurement will be done again on completion.


December 20, 2010


Shuttering startsLast day of walls construction


The mistris (masons) are strange creatures. Since yesterday mistri Isa Khan has been asking me to arrange some 4,000 more bricks by the evening because he and his team wanted to begin work early and warned me that if there were no bricks, they will not work. Despite my estimates that the bricks already lying around the plot would be enough, I ordered expensive bricks. The one which I had ordered two days ago had got delayed at the source because of Muharram holidays. So I had no option but to waste extra thousands.


When I reached at about 3.30pm, I noticed that the old stock had not yet been consumed and expensive bricks were piled up unused. When I asked he said that these will also be used, but till sunset when I left they were still unused. Though this stock would be used now in boundary wall or the first floor, but the way these mistris create panic is disgusting. For years they are doing the job and do not know such basics as how much material they would need. He had also asked for five more cement bags, but only one was used.


Shuttering for the lanter (roof) has started. Have to buy more steel, sand, gravel large quantity of cement and arrange for water on the concrete pouring. Another good thing was that waster supply was sufficient to top up the tank.


December 21, 2010


shuttering at car porch side


Shades size remained on my mind today. The contractor called and asked me what size of shades I would prefer. He suggested that two feet extension of roof slab would be enough. I checked and some people said it should be three, some said three would be too big and two is enough. Bahria Town allows only one and half feet. The bigger the shade, the larger the covered area and more the cost. But I need them so that one could move out in the balconies easily, place a geyser and also dry clothes. Home government wants three feet wide, so have to tell the contractor first thing in the morning.


The contractor says that concrete would be poured into roof on Monday or Tuesday. Too bad because it would be hard to get leave on these days as two colleagues are on leave. Will have to do something about it as my presence is essential on the lanter day.


December 25, 2010


Pillar removed


Demolished a pillar yesterday which was obstructing the space. Now the porch's outer pillar will be bended towards the corner pillar and this space could be used for car parking purpose. I had asked in the initial stages, both my contractor and architect, but they did not listen. Contractor had said it could not be done, while it could be done and I have seen in several houses that porch roof can be reinforced by other means.


I had to made several on-spot changes to align the windows of drawing room and first floor. Had to move out a bathroom from the first floor room, above the drawing room towards the terrace. This will make the room harmonious and capacious. Also feel that bathroom vent size is too small, but it can be widened once the lanter is done.


Today ordered 200 bags of cement and two trucks each of gravel and sand for the big day. The cement is down to 289 rupees per bag which is a good news at least.


I am on duty today and will be off on Sunday and lot of work to do like buying additional steel and engaging an electrician to do points for fans and lights in the roof and it is done before the lanter. Two colleagues have gone on leave at once so I feel bit stressed and worried about leave for lanter preparations.


[Please keep visiting for updates]

Comments

zainulhassan said…
Good luck Masroor bhai
Masroor said…
Thank you so much Zain bhai, remember me in your prayers. Long time no see!!! but your kind words really boosted my morale,

regards
Asmatullah Niazi said…
its great. i ll love to be benefited from experience .
Masroor said…
Thanks Niazi bhai.....if it failed to make me insane :-)
Good luck with your work. I got a friend who deals with construction in PWD. They make some plazas. Really a nice friend and younger to me. If you want I can forward you his contacts !
Taimoor Khan said…
Nice Share Masroor Bhai. I live in Police Foundation D Block next to the media town. Will love to meet u someday btw I'm a civil engineer, ur welcome anytime in case u need any technical advice.

Regards

taimoorkhan@pw
Atif Khan said…
Dear Masroor,

Thanks for sharing your detailed experience. It looks very helpful for people who are and would be building their own home and I am one of those people as I am planning to get a plot and start construction on that. I will be reading your blog regularly to avoid all the mistakes you have made. Keep writing. Thanks again for sharing and wish you all the very best.

Regards,
Atif
Mujtaba said…
Dear Masroor Bhai,

Although,I have the experience of building the houses but really impressed with your blog. We all have to go through all these processes but we can't express those.

Well done effort......
Best wishes,
Syed Mujtaba Shahid
Bahria Town, Islamabad
Imran said…
Masroor Bhai House Building is an Lifetime Headache, and need alot of patience and also Experience as i have intention to build house in Jinnah Garden, so your experience will help me, but i am more keen for giving all in all contract to some contractor on Turn Key basis but cost is extra high.

Wishing you best of luck for your project as working and constructing home is not easy job, but May Allah make your project smooth as silk. Ameen
Vajih102 said…
Congrats on beginning this mega project at such a young age! Should you be needing any help building/offer advice/supply materials and vot not related to your uphill task, do contact Mustahsin Qamar at 03345394454. His office is in PWD as it is. It is relatively new but their experience dates to over a decade i guess. You may see a few of his projects in Korang Town as well.
Masroor said…
@Haseeb. Thank you very much. I only need prayers from very nice friends like you.

@Taimoor. Thanks Taimoor bhai, you are most welcome anytime.

@Atif. Thanks. Yes the idea behind writing my experience is mainly that other aspirant house builders should have an idea what difficulties they are going to encounter and what mistakes that I will be making unintentionally, how they could avoid it.

@Mujtaba bhai thanks for everything and your constant guidance and support means a lot to me and I could never have started this project without your help.

@Imran. Thanks and good luck for your project. Giving "with material" contract is though very convenient, but it is way to expensive and you are never sure if the quality of the things would be up to mark as the contractor then would do the purchasing and save on everything he can for himself.

@Wajih. Thank you very much, I will contact Mustahsin.
2z said…
My dad is about to finish his home in Bahria Town phase 3 and believe me keep going on money will definitely come.
Masroor said…
@2Z. Thanks a lot. I am glad that you are about to move into your new house. May Allah bless your new home and bestows prosperity and happiness. Your kind words have really boosted my morale as I was worried over money.
Capt.Shahzad said…
Gone through all of ur work details.I know its extremely painfull to make the things done in given time even after spending the hard earned money .Seeing the current increase in construction material it's way difficult to set the approximate limit of budget for Construction.
Issues related to your budget will be solved insALLAH.Your hard earned money ll surely pay u off in terms of relaxed life for u and for your family . Ameen.
Masroor said…
Thanks Shahzad bhai. Remember me in your prayers, regards
fauzia shahid said…
very nice Allah naseeb karray ameen
Masroor said…
Thanks a lot Fauzia and Summa Aameen.
Anwar Shakir said…
Hello,Masroor
Great work. I am very astonished to see your project and your unique mind. I know you from last 7 years ,but by 2010 I feel that you have another Masroor in your body. I congratulate you for construction of house which is too difficult work but you have energy for this. How much fund (money) you have allocated for this ?
Insha Allah I will remember you in my prayers.
Masroor said…
@Anwar. Thank you very much for your comments. If I am lucky I will be able to make single floor in two million, but costs of building materials have started rising insanely, so I fear that it would be more than that.
Shakeel Ahmed said…
Nice work Masroor Bhai.........sharing ur house construction experience is a great deal and i hope every body is learning a lot from ur experience. As far as i am concerned this is going to be a great help for me as i am too planning house construction in media town C Block. can i contact u some time later for more help?? thanx
Masroor said…
Dear Shakil thank you very much. I am glad that people viewing my post are benefiting from my experience in any way. You are most welcome to contact me for any guidance of help, best regards
GOod GOing. I am following
hurriya said…
Thank you.its so informative.
Sajjad Azhar said…
Salam ,
This is unique work butt i have a suggestion if u can make a web all about media Town and how to build a home , i think it is really needed ,
Aijaz Mahar said…
Its nice to know that you are building your house and we must learn from your experience.
Masroor said…
@Sajjad. Thanks. I have a separate thread about Media Town http://www.masroor.com.pk/?p=22 . I leave it to Press Club to include a section on their website.

@Aijaz. Thanks
Mateen Haider said…
Thanks a lot for sharing a lot of information about construction of house in Media Town. you are the only one from media community who has shared information about their experiences. Good luck and Allah Almighty give you long life and your dream of getting a very sweet home may materialize as soon as possible.

Regards

Mateen Haider
Dawn News, Islamabad.
Masroor said…
Thanks a lot Mateen bhai for your kind words and prayers and I wish you the same, regards
MASHHOOD said…
Hi Masroor bhai what is latest progress at site of your house
Masroor said…
Well there was holiday on 9th and 10th Muharram and progress before this break is in this post. Anyways, we have reached door level and completed beams and columns. Tomorrow hope to raise walls up to roof level and after that shuttering and steel work will start for the ceiling.
Khurshid Khan said…
This is a great effort and I think a great public service for sharing your valuable experience. Please keep up the good work....and stay blessed.

Sincerely,

Khurshid
Saima said…
I just came across this thread while searching for some one having experience with Media town.I want to buy a plot and then build a house in Media Town.I would appriciate if you can guide me with the market price of 10 marla plot in this locality.
Regards
Saima said…
Please also let me know about the issue of transfer of plots in Media town (i guess not open).
Masroor said…
No idea about price or transfer. I just focus on building my house.
saima said…
ok Thanks
Ijaz Agha said…
Dear Masroor Bhai,

I am very impressed with your blog. The details there are very helpful for those people who will be starting their own houses. Thanks so much for updating the list for me for all the steps you took to complete your house. I will be uploading this list on property forum so that people can benefit from it. All credit goes to you as I never seen such infromation on the net. Regards, Ijaz
pardesifr said…
AoA Bahi,

Great information you shared,

Please update the information till completion

Also if you can post a updated breakdown of all expenses you had till now (material and mazdoori and contractors expenses)

What will be the total price of 2 story house on 10 Marla in Bahria town rawalpindi.

This will help a lot :)
sanaullah,,khan said…
Dear..AOA
You..did..a..remarkable..job...Congragulation..........
I..have..a..plot...in.B-17.........I...was...intrested..to...develop...basic..understsnding...before...to..finally..decide..to...go..for..construction...your...experience...link..gave..me.very...good..insight.
Thanks...
Please...share..your...next...events...also...I..am..anxitially..waiting..for...it.More..ocer...i..request..others..also...to..share...their..experiences...I...hope...this..would..be...a.nice..and..intresting

Thanks

sanaullah..khan
syed muhammad tanveer said…
salam masroor bahi u did a remarkable job and for dis you help a lot of peoples who dont have any idea and they trapped to a fake builder who cheat him very badly and at the end he loose his money time and his dreems.
Naeema Farooqi said…
I love this blog and the detailed account of house construction. It is a huge task to undertake in Pakistan and it certainly gives valuable advice to those contemplating building their home. All the best and JazakAllah for sharing!
Masroor said…
@Naeema. Thank you so much for your kind words.
Raja Adeel Anwar said…
Its great job done by u , i also just finished my home construction work and i know it a lot of panic , specially to make arrangements for all the stuff,
plz send final pictures.
ALLAH AP OR AP KI FAMILY KU YA GAR NASEEB KERE....AMEEN
Masroor said…
@Adeel. Thank you so much for your prayer and kind words. May Allah bless you. Sorry for replying late as I was pre-occupied with shifting
hasnain haider said…
dear masroor u have given us very valuable information about house construction. i have realized that this work is extremely difficult in pakistan. i want to start the business of house construction on a small scale. hope i dont face so much difficulties as u have faced. can u give me anyother valuable advice which u havnt mentioned in ur blog? finally well done man!
Arshad Hassann said…
Best wishes for your new home. Excellent demonstration of your project.
I have a 10 marla plot (40x68 feet) and trying to collect home plane suggestions / samples to finalize my home plan. Can you please advise;
- Your plot size (width x depth) in feet?
- individual coverd area of 1st & 2nd floor?
(sizes in your home plan on this site are not readable)
Thanks for your help in advance :)
Masroor said…
@Arshad. Many thanks for your email. Plot size is 40.9 x 68.8. GF covered area 2,339 sq feet, FF 2,045 total 4,384. First decide what you want, I mean how many rooms and in which part of the house you spend most of the time and make them accordingly. Some families spend most of their time in television lounge, so it should be bigger as bedrooms are only meant for sleeping, so no need of bigger one. You can also make the DD smaller as in most of the cases it is the place used by guests not very often. If you have frequent guests coming to live with you, you need a guest room with bath. First draw a concept according to your requirements and then discuss it with an architect you will get a better house in the end, regards
Arshad Hassann said…
Thanks for quick response.
You are right most of the time is spent in TV lounge. I'm planing lounge size 13x11 feet.
My preference is single story home. having 02 bedrooms with bath, 01 Guest room attached to DD. Small size drawing room with space of 1x3,2x2 seater sofa set is enough. I'm planing dinning room connected to a part of lounge that can be seprated by curton wall so that dinning table can be used for guests often otherwise family can use it in routine. I don't need dress rooms just want a long size dress cabinet

What is your bed room, TV lounge and kitchen size?

Best wishes / Arshad
Masroor said…
Bath sizes
7.9 x 6.3
5.3 x 8.0
12.0 x 3.4

Dresser second bath
5.3 x 5.7

Beds
13.6 x 14
12.0 x 14
12.0 x 9.6

TV lounge
21.6 x 16.9

Drawing
15.0 x 18.0

Porch
24.3 x 12.6
Syed AwaaZ Siddique said…
masroor bhai me apna plot ka map banwana chata hon or ziyada time nahi hai jaldi karwana chata hon plot size 240 yards in karachi masroor bhai help kar sakte hain ap ??
Masroor said…
All you need is a good architect
Syed Aamir Hashmi said…
Masroor Sb.
Really its a great effort you have done by providing step by step construction of your house. I must appreciate. I want to construct my house and need a BOQ to estimate the cost with latest prices. If you have BOQ of your house kindly forward me I shall be grateful for that.
Masroor said…
Dear Amir, thank you. I don't know the term BOQ, but I have posted the details of my expenses in one of the threads
Syed Aamir Hashmi said…
Thanks Masroor Sb I got the detail of expenses. BOQ means bill of quantities. means as per drawings & sizes of construction how much material shall be required i.e. Cement, Sand, Gravel, Steel, Sanitary, Pipes etc. I am trying to prepare that for a 10 Marla House if I got the quantities then at any stage anyone can find the cost by changing the current rates of material. That shall be helpful for others also. Your data of expenses is very helpful I am trying to find quantities of material from Sheet 2.
It's an excellent account of your DIY home building project. We've made a mention of it on our website here: http://oasisbuilderspakistan.com/a-journalistss-tale-of-building-his-home-in-pakistan-a-diy-project/. The photo used from your post has been duly credited to your blog. Keep us posted with your latest pursuits.
Malik Tanveer Hassan said…
Masroor Sb.
Really its a great effort you have done by providing step by step construction of your house. I really appreciate your efforts. Actually I also want to construct my house next month and I will follow this pattern..... Now may i see your house current front face view so that i can have as idea that how its looks ....
Masroor said…
Malik Sb.
Many thanks for your comments. My house is still not finished due to funding problems and currently it looks like this from outside.

http://www.facebook.com/photo.php?fbid=10150452938751661&l=c2a1c90d80
Amir Shakoor Hashmi said…
Dear All,
I am going to construct a 10 Merla house at Baheria Town Lahore and i need BOQ & Map.

Anybody can favor me on above mention email
Masroor said…
As far as I know Bahria Town has its own designs and layouts and you have to select only out of their designs and layout. You cannot modify anything. You should call/visit Bahria Office for further guidance.
MAB said…
I want to build a 1 kanal house in architect society, I nee bill of quantity, if anyone have, please share
huny said…
Good effort you can find home elevations from a site marla99.com
Sajid Hussain said…
dear sir!
aoa. sir main ne apne ghar ka map teyar krwana hai kya aap mare help kar sakte hn?
Aman said…
Mr Masroor
AOA I wants to construct my house in airport society Rawalpindi I need house plan, can you help me in this regards that from where I can get the same. I need an honest architecture and an hones contractor also if you know them please guide me.
My plot size is 06 Marla (30x50) can you tell me the estimate expenditure for ground+01 house. I shall e very thank full to you.

Thanks and regards
Masroor said…
Deare Aman. My architect was not bad. His office is in PWD soceity. I can also refer you to a contractor, but believe me there is no such thing in Pakistan which we call honesty. You have to pick and chose carefully and then remain over their heads. If you are lucky you will get less troubles. Wish you happy construction and your own roof.
Aman said…
Masroor Sb
AOA Is this compulsory to get the plan from an architecture ? Can we copy the anyone's map and submit the same for approval ? as I am out of country and I can get only 01 month annual leave, I want to build a house in Pakistan what to do? What is the best way for construction, please don't mind can you share your experience with me and guide (I am just new in this field) and don't want to be cheated. May I know the rough expenditure for my house (30x50) 04 beds+04 baths+kitchen+store etc. Please guide me must about the expenditure.

Thank you very much
Khan Abdul Qayyum said…
Yeh, i can help you to prepare BOQ
Aman said…
Mr qayyum.
I just want to know the rough expenditure for my house. Pls send me the rough amount.

Thanks
asif ali said…
salam to all ,,
is ther any simple way to leran how to do estimate of a 4 rooms house... ?
anybody can help me .....!
junaid said…
AOA.Mr.aman.
i had the same problem what you are facing.i had my house built while living in uk it was very hard to find a good contractor but i manage to find one.anyways i asked him about the estimate and he said it should not cost no more than 27 to 30 lacs any more than that than you are being ripped off.
Masroor said…
Check with some contractor how much per square he will charge for material and labor both and multiply with the covered area to have an idea.
Aamir said…
Aoa Junaid sb,
These days i am making feasibility of house construction business in Rawalpindi/ Islamabad and what i figured out that the cost including material is 1200 to 3200 RS psf. and if you make it with hollow blocks then the structure cost will be reduced down to 30%. and to speed up the process you can use prefabricated beams etc. and dont use barbels on the floor just use concrete floor and use staining to make different patron. also you dont need to keep concealed electric works in ceiling as these days plaster ceiling is quit inn in the market. and there are many time saving techniques concerned to save time and cost.
good luck with your project.
ahsan said…
house construction and maintains on email me ahsan-jee@hotmail.com
normal rate is only structure RS 230 per
sft
Bilal Haider said…
Asslamo Alaikum.

I read your blog quite a long time back,but didn't get a chance to in touch with you,i would really great full if you can put few informations in simple words which would help alot to others who are planning to start their own sweet home.

Plot size.........................................................10 Marla?
Coverd Area...................................................1234 Square Feet
Ground Floor Area..........................................1234 Square Feet
First floor Area...............................................1234 Square Feet
Roof level.......................................................1234 Square Feet
Cement total bags........................................123 Nos
Steel total KG or Ton................................................1234KGS
Bricks.............................................................12345Nos
Sand..............................................................Trolly or 123 Cubic feet
Bajri................................................................Trolly or 123 Cubic feet
Marlble Filling...............................................................Trolly or 123 Cubic feet
Bath room tiles price............................................................123 Square Feet
kitchen tiles price................................................................123 square feet
Wiring cost..........................................................................1234 Rs
Waterproofing cost at roof........................................................1234 Rs
Door Cost.........................................................................1234 Rs for X nos with name of material
Cupboard/Almirah in bed rooms..........................................1234 price
Any false ceiling works/Gypsum work.......................................123 price



Thanking you in anticipation.
snk said…
Heay there,

Good to have some first hand info on constructing a house but I gotta say this man - after seeing those ten thousand photos, I have to ask that did you ever go home or did you start living over the construction site. It is like a never ending a horror show. Does it happens to everybody in Pakistan? But thanks all the info.
Masroor said…
Thanks for your comment, yes it is a horror story and only few insane people like me share it. There is another way that you give tons of money to a contractor, he buys everything and build a house for you. In most of the cases, a few years later real things start showing up.
Masroor said…
I am really not updated about current prices. All the details, expense sheets are available in construction posts on this site.
madeelhassan said…
Asslamoalikum!Its really nice effort the details that are present.However Being a civil engineer, this is normal routine work for me.I have seen some common questions at the blog Answer to all of them ( in summary ) are
1-Bill of Quantities (BOQ) --BOQ is not fixed with area of house ( for example-5 marla 10 marla).Actually it is associated with Architectural drawing and respective details.By getting BOQ of one house of 5 marla can give u a guess for your own 5 marla house.
2-Sequence of works.----Its better to get your house modelled with softwares like SWEETHOME3D or GOOGLE SKETCHUP so that you will understand your home in better way
3-Rates ----These vary from market to market as well as quality of manpower.However construction of house on labour rate and material provided by clients will keep client safe with respect to quality.Currently i am putting some information .More will be available at my blog. http://madeelhassan0.blogspot.com/ you can get some information about marble http://madeelhassan0.blogspot.com/2013/03/marble.html Soon you will be able to get all information about house construction like rates,BOQ,3d modelling , pipe works, renovation works,structural stability etc.Join me at my blog . It will be free http://madeelhassan0.wordpress.com
Regards Adeel hassan
madeelhassan said…
Asslamoalikum!
Its really nice effort the details that are present.
However Being a civil engineer, this is normal routine work for me.
I have seen some common questions at the blog
Answer to all of them ( in summary ) are
1-Bill of Quantities (BOQ)
BOQ is not fixed with area of house ( for example-5 marla 10 marla).Actually it is associated with Architectural drawing and respective details.
By getting BOQ of one house of 5 marla can give u a guess for your own 5 marla house.
2-Sequence of works.
Its better to get your house modelled with softwares like SWEETHOME3D or GOOGLE SKETCHUP so that you will understand your home in better way
madeelhassan said…
3-Rates ---These vary from market to market as well as quality of manpower.However construction of house on labour rate and material provided by clients will keep client safe with respect to quality.Currently i am putting some information .More will be available at my blog.
http://madeelhassan0.blogspot.com/ you can get some information about marble http://madeelhassan0.blogspot.com/2013/03/marble.html
Soon you will be able to get all information about house construction like rates,BOQ,3d modelling , pipe works, renovation works,structural stability etc.Join me at my blog . It will be free http://madeelhassan0.wordpress.com/
Regards
Mohammad Arif Shaikh said…
First of all Masha'Allah and many congratulation for your house. When I started looking at the pictures and reading the article I was in an engrossed state with my hand stuck on my face like Alama Iqbal and at the end of last picture I had a red hand print on my face. But job well done! I am mostly scared of seepages and looking at a few leakages in your project, I am wondering do you see any after the construction is completed?
Masroor said…
Shaikh sb many thanks for your feedback. Alhamdolilah there is no leakage or seepage so far. Last year put chips on porch roof, rooftop and "mumty" roof because water was accumulating and had started seeping through. But now there is no such thing.
Mohammad Arif Shaikh said…
Masroor Saheb I want know how much did you pay to your architect for the entire architectural work, I mean per sqft there is a renowned architect a real famous one who has quoted me Rs45 per sqft. Secondly, desperate to see the final picture of the house.
Masroor said…
Shaikh sb we got a special rate due to bulk clients
Rizwan said…
Asalam O Alikum Sir,

First of all, I would like to congratulate you on your house. Your blog posts have been really helpful as we are planning to start construct our own house in Lahore in near future. Hence, i have been researching about the construction. While my research, your house plan layout met our requirements and we are looking to use your house plan as a reference for our house map.

The picture resolution you posted on your blog is low and I am unable to understand the dimensions. Could you please send me an high resolution picture of your map?
I'll be thankful, sir.
Regards,
Rizwan
Dr. Abdul Karim Rehmatullah said…
Dear Masroor Shaib, I am constructing my house in Banigala Islamabad. The contractor is asking too much money for the filling. Kindly send me the contact no. of the person who did filling of your plot. I will be thankful. Dr. A.K.rehmatullah, Madina Al Munawara, KSA
Masroor said…
Dear Abdul Karim sahib, I got the plot pre-filled. Check with several contractor in your area and get rates. Thanks.
Masroor said…
Many friends have been asking what is the cost of construction of different plot sizes. Well calculate the covered area you are going to build and multiply with the figures below. I have basically collected the following information from the Internet for the benefit of the readers.

The cost of building a house varies on the quality and the finishing.

Raw (structure only - cement/steel) cost is about Rs. 1,200 per square foot.
Developed (floors, windows + doors) cost is about Rs. 1,800 per square foot.
Finished (all completed, including bathrooms, lighting, kitchen, basic woodwork, etc.) is about Rs. 2,200 per square foot.
Anything after this is silver polish.

Someone in Karachi recently built his house at about PKR 2,700 per square foot. He started out expecting it to be around PKR 2,200, but:

a) There has been considerable inflation in the cost of raw materials, like cement and steel. Contractors have also inflated their charges by about 20% from last year.

b) When you get down to building it, usually you end up going for the finer finishes (assuming you're building to live).

Contractors are able to build houses for less than PKR 2,000 per square foot. They are able to achieve this cost point by putting in cheaper structural materials, like steel, cement, electric wiring etc. And of course, they build tampletized houses and drive efficiency from there.

To summarize, if you are building a house for yourself, keep a budget of around PKR 2,500 / foot. And don't buy houses built by contractors (thakaydaars).
Khan said…
Mashallah. I rate you. I am in the same boat as you and want to build my house in Islamabad. Can you provide me with any other links of similar experience. I am in particular need of where to resouce good materials from prices and off course a good architect.
sohail said…
Sir g nice workd u did ...crazy effoerts by u
Masroor said…
Thanks. Lots of learning in it though hard way. But in Pakistan only luck counts, no matter how smart are you :)
Muhammad Nauman said…
Masroor Sb.,
I intend to start construction of my own house in F-15/1 Islamabad in February 2014 inshAllah. The covered area is evaluated as around 7,000 Sq. Ft. (Basement, Groud and First Floor). My main concern is budget; I want to build a grey structure and boundary wall but finish only two floors. We have only 8.5 Million for constuction of house at this time. Therefore;

1. Do you think would that be possible to finish all three floors within this budget?
2. Do you think would that be possible to only finish two floors within this budget?

I would be wholeheartedl grateful for your kind guidance, Masroor Sb.

Best wishes,

Nauman
Masroor said…
Dear Nauman sb prices of material are rising all the time so I will not be able to give you an idea. The only thing which can give you a rough idea of cost is the prevalent market rates of construction, with or without material. For instance if the prevalent market rate for per square feet of construction with material is 1,800- 2,200 hundred rupees (up till finishing), multiply it with your covered area and you will get a figure.
Hassan said…
AOA, @ Muhammad Nauman
In this budget you have have the structure done all of it but finishing depends of what kind of finishing your after.you can get in touch with me on hassan786_99@yahoo.com and give me the plot size and ill get back to you with more accurate estimate.
Nauman said…
Dear Masroor Sb.,
That really helps. I appreciate that, God bless.
izatwaqarizat said…
Jobs and best construction of houses Plots available in bahria town DHA Islamabad different sizes for details contact izatwaqar at gmaildotcom also best construction and finishing of houses please see already constructed houses Dear JobSeeker, representative Great opportunities for you in United Nations Organization Send your CV details of setup for receiving further details
imtiaz said…
After reading the above mentioned comments, I have concluded that one should purchase a built house rather spoiling his 2 years of ones precious life.
Newstopline said…
Visit www.newstopline.com and get the latest news updates from the leading news papers on one stop! We cover news from all areas; be it sports, politics, current affairs, social, entertainment, or business. Get anything and everything on one platform. Join us and stay updated 24/7 all year round.